Tuesday, November 3, 2015

Project Completed!!

Work Completed Last Week:
·         Asphalt surface paving.
·         Miscellaneous repairs of items identified during final walk-through.

With the completion of the asphalt surface paving this week, along with a few other miscellaneous items completed, the major construction along the project site is now completed. There are still a few outstanding issues that we are addressing on an individual basis and will completed in the near future.

We would like to thank all the residents within the Glenayre Park neighborhood for dealing with the construction over the past two years. We understand what an inconvenience construction causes to your daily lives. We thank everyone for their patience and understanding. We are hopeful that you are satisfied with the end result.

Within the next few weeks the Village of Glenview will send out a survey for you to complete. We appreciate your time in completing the survey as it assistance with future projects throughout the Village.

This will also be the last Blog Post for the project. Again, we hope you found the information provided beneficial.

If you have any additional concerns, please contact the project manager, Robert Steele, at 847-904-4423

Monday, October 26, 2015

Sod Completed. Surface Paving this Week.

Work Completed Last Week:
·         Installation of topsoil and fine grading landscaped areas.
·         Sod Installation
·         Final Walk-through to find areas that need repair.

Work Anticipated This Week
·         Paving of asphalt surface
·         Making final repairs to items as identified with final walk-through.  

The paving of asphalt surface was pushed back to allow for sufficient time to get the sod restoration completed. A thin layer of oil will be placed on the existing asphalt surface prior to the final layer of asphalt being paved. Sand will also be placed on driveways and the roadway. This will help from tracking the oil on your concrete or brick driveways as well as help splattering on your vehicle. We do ask that you drive slowly over the fresh layer of oil.

Asphalt surface paving is scheduled for Monday, October 26th.  We will ask that you minimize your trips along the roadways and no parking will be allowed on the streets. Access along the streets will also likely be restricted due to the paving operations and number of trucks within the area.

Once the final layer of asphalt is installed, the major construction operations of the project will be completed with a few minor repairs and restoration items to be completed.

Thanks again for all your patience during these past several months you have been living in a construction zone.

Monday, October 19, 2015

Final Surface Paving and Sod Restoration This Week.

Work Completed Last Week:
·         Installation of topsoil and fine grading landscaped areas.
·         Televising of new underground utilities
·         Final testing of underground utilities
·         Miscellaneous site clean-up and tasks

Work Anticipated This Week
·         Topsoil Installation and final landscape grading
·         Sod Installation
·         Making final repairs to items as identified with final walk-through.
·         Paving of asphalt surface 

The current schedule has the contractor completing any minor repairs and finishing the sod installation the beginning of this week with the final layer of asphalt pavement installed on Thursday or Friday. A thin layer of oil will be placed on the existing asphalt surface prior to the final layer of asphalt being paved. Sand will also be placed on driveways and the roadway. This will help from tracking the oil on your concrete or brick driveways as well as help splattering on your vehicle. We do ask that you drive slowly over the fresh layer of oil.  

Residents will be notified of the exact day for final asphalt paving. We will ask that you minimize your trips along the roadways and no parking will be allowed on the streets. Access along the streets will also likely be restricted due to the paving operations and number of trucks within the area.  

Once the final layer of asphalt is installed, the major construction operations of the project will be completed with a few minor repairs and restoration items to be completed. 

Thanks again for all your patience during these past several months you have been living in a construction zone.

Monday, October 12, 2015

General Clean-Up Last Week. Sod Installation This Week.

Work Completed Last Week:
·         Televising of new underground utilities
·         Final testing of underground utilities
·         Landscape grading
·         Installation of topsoil
·         Internal lining of sanitary sewers along Glenayre Drive
·         Miscellaneous site clean-up and tasks

Work Anticipated This Week
·         Topsoil Installation and final landscape grading
·         Sod Installation
·         Complete televising of new underground utilities

The contractor has continued to perform miscellaneous tasks around the project in preparation for paving the final surface layer along the entire project site. The final surface layer is typically one of the last items completed to minimize the amount of construction traffic on the surface. Currently, the final surface paving is scheduled for the week of October 12th.

At this time, residents can begin contacting their irrigation and brick driveway contractors to begin having those items restored.

Monday, October 5, 2015

Final Testing of Underground Utilities On-Going

Work Completed Last Week (Glenayre Drive):
·         Adjust manhole structures within pavement
·         Complete asphalt driveway restorations
·         Continued with landscape grading
·         Miscellaneous site clean-up and tasks 

Work Anticipated This Week
·         Televising of new underground utilities
·         Final testing of underground utilities
·         Topsoil Installation
·         Sod Installation

The contractor has continued to perform miscellaneous tasks around the project in preparation for paving the final surface layer along the entire project site. The final surface layer is typically one of the last items completed to minimize the amount of construction traffic on the surface. Currently, the final surface paving is scheduled for the week of October 12th.

At this time, residents can begin contacting their irrigation and brick driveway contractors to begin having those items restored.

Monday, September 28, 2015

Concrete Curb & Gutter and First Layer of Asphalt Completed. Landscape Restoration to Begin

Work Completed Last Week (Glenayre Drive):
·         Concrete curb & gutter installation
·         Fine grading of roadway
·         Rough grading of landscape areas behind cub & gutter
·         Paving of first layer of asphalt pavement
·         Asphalt driveway restorations

Work Anticipated This Week
·         Adjust manhole structures within the pavement
·         Topsoil installation
·         Fine grade landscape restorations
·         Sod installation
·         Perform miscellaneous testing prior to final asphalt surface
 
Thank you to all the residents along Glenayre Drive that have been without access to your driveways for almost 2 weeks. Your patience and understanding has been greatly appreciated. With the first layer of asphalt pavement being completed, the amount of dust will be greatly reduced, as well as providing a smooth surface to drive on.

The contractor will continue to perform landscape restorations and begin performing final project testing for the next few weeks. Once all inspections and tests have passed, sod installed, and other miscellaneous tasks completed, the final asphalt surface layer will be installed along the entire project site including Glenayre Drive, Glenridge Drive, and Glen Court.

Thank you again to all the residents within the project site has you have been dealing with the dusty conditions and rough roads for several months now. Hopefully, you are beginning to see the end of the light and pleased with the final project.

At this time, residents can begin contacting their irrigation and brick driveway contractors to begin having those items restored.

Monday, September 21, 2015


Work Completed Last Week (Glenayre Drive):

·         Install concrete curb and gutter from Glenview Rd. to Westview Rd.

·         Continued excavation of roadway and installation of new aggregate base materials.

·         Installation of curb string line and preparation for curb installation from Westview Rd. to Central Rd.


Work Anticipated This Week (Glenayre Drive)

·         Install concrete curb and gutter from Westview Rd. to Central Rd.

·         Backfill behind new curb and gutter.

·         Prep for asphalt and concrete driveway replacement.

·         Install asphalt and concrete driveway pavement.

·         Pave first two layers of asphalt roadway pavement.

 
The major roadway reconstruction of Glenayre Drive will continue this week as concrete curb & gutter poured, and first two layers of asphalt pavement paved. The current schedule due to a rain delay has concrete curb & gutter pouring to begin the week of September 21st and asphalt pavement installed by end the of the week, depending on work progress and weather conditions. Residents will be notified of driveway restrictions as the scheduled is finalized.

 
Thank you again for all your patience and understanding.

Friday, September 11, 2015


The major roadway reconstruction of Glenayre Drive will continue this week and last for the next 2 weeks as the roadway is excavated, new aggregate base is installed, concrete curb & gutter poured, and first two layers of asphalt pavement paved. The current schedule has concrete curb & gutter layout, preparation, and pouring to begin the week of September 14th and asphalt pavement installed by end the of the week of September 21st, depending on work progress and weather conditions. Residents will be notified of driveway restrictions as the scheduled is finalized. 

 
Work Completed Last Week: (Glenayre Drive)

·         Excavate existing roadway materials and install new aggregate base course.
·         Excavate and re-install new aggregate base materials in areas where the existing materials are poor
·         Remove existing pavement at entrance to neighborhood at Glenview Road and Glenayre Drive

Work Anticipated This Week (Glenayre Drive)

  • Continue excavation of existing roadway materials and installing new aggregate base course.
  • Continue excavation and installing new aggregate base materials.
  • Installation of curb string line and preparation for curb installation on Glenayre Dr.
  • Install concrete curb and gutter on Glenayre Dr. by the end of the week.
The contractor will continue to grade and clean-up Glenridge Drive and Glen Court in preparation for landscape and sod restoration over the next few weeks.

Thank you again for all your patience and understanding.



 
 
 

Monday, September 7, 2015

Glenayre Drive Roadway Reconstruction to Begin This Week

Work Completed Last Week:
·         Completed asphalt driveway restoration along Glen Court & Glenridge Drive
·         Landscape grading along Glen Court & Glenridge Drive
·         Raise manhole frames and grates within the pavement along Glen Court & Glenridge Drive
·         Removed existing driveways and installed temporary access along Glenayre Drive
·         Lowered manhole covers below grade along Glenayre Drive

Work Anticipated This Week (Glenayre Drive)
·         No work on-site on Labor Day
·         Excavate existing roadway materials and install new aggregate base course.
·         Excavate and re-install new aggregate base materials in areas where the existing materials are poor.
·         Remove existing pavement at entrance to neighborhood at Glenview Road and Glenayre Drive.
 
The contractor will continue to grade and clean-up Glenridge Drive and Glen Court in preparation for landscape and sod restoration over the next few weeks.

The major roadway reconstruction of Glenayre Drive will begin this week and last for the next 3 weeks as the roadway is excavated, new aggregate base is installed, concrete curb & gutter poured, and first two layers of asphalt pavement paved. The current schedule has concrete curb & gutter layout, preparation, and pouring to begin the week of September 14th and asphalt pavement installed by end the of the week of September 21st, depending on work progress and weather conditions. Residents will be notified of driveway restrictions as the scheduled is finalized.

Thank you again for all your patience and understanding.

Have a safe and enjoyable Labor Day Weekend.

Friday, August 28, 2015

2 Layers of Apshalt Paved on Glenridge. Roadway Reconstruction to Begin on Glenayre

Work Completed Last Week (Glenridge Drive and Glen Court):
·         Paving of first two layers of asphalt pavement.
·         Landscape grading behind previously installed concrete curb & gutter.
·         Fine grading of roadway
·         Asphalt driveway restoration
·         Concrete driveway restoration
·         Access to driveways is allowed as of Friday, August 28th

Work Anticipated This Week
·         Install and grade topsoil along Glenridge Drive and Glen Court
·         Removal of existing driveways along Glenayre Drive, temporary access will be provided.
·         Staking / Layout for roadways improvements along Glenayre Drive
·         Removal of existing asphalt pavement along Glenayre Drive
·         Excavating of existing materials to sub-grade along Glenayre Drive
·         Installation of aggregate base along Glenayre Drive

Driveway access has been restored along Glenridge Drive and Glen Court due to the concrete curb & gutter installation and asphalt paving. Thank you to all those residents that were without access to your driveways for approximately 10 days, your patience and understanding was greatly appreciated.

The contractor will continue to grade and clean-up Glenridge Drive and Glen Court in preparation for landscape and sod restoration over the next week or so.

The contractor will also begin the roadway reconstruction phase along Glenayre Drive. Work will include removal of existing driveways, construction layout, roadway excavation, and installation of aggregate base course.

The current schedule has the contractor performing concrete curb & gutter installation and asphalt paving beginning the week of September 14th through September 24th, depending on work progress and weather conditions.

Thank you again to all the residents that have been living in the construction area for the past several months. We understand the difficulties and inconveniences that are caused with living through a construction project and are doing everything possible to make the project go as quickly as possible.

Monday, August 24, 2015

Roadway Improvements along Glenridge Drive and Glen Court Continue

Work Completed Last Week (Glenridge Drive and Glen Court)
·         Completed roadway excavation and installation of aggregate base course
·         Grading, setting string line, and structure adjustments in preparation of concrete curb & gutter
·         Pouring of concrete curb & gutter.

Work Anticipated This Week (Glenridge Drive and Glen Court):
·         Grading and backfilling along back side of curb & gutter
·         Grading of roadway in preparation for asphalt pavement
·         Grading for asphalt driveway replacement
·         Installation of first layer for asphalt driveway replacement
·         Paving first layers of asphalt pavement, scheduled for Wednesday or Thursday.

Driveway access to those residents along Glenridge Drive and Glen Court is scheduled to be allowed by Friday, August 28th. Access might be allowed sooner depending on work progress.                                                                                                                                                                                                                        

The week of August 31st, the contractor will continue with landscape grading, topsoil installation, and general site clean-up prior to the Labor Day weekend.

The schedule for roadway reconstruction along Glenayre Drive is currently being evaluated to determine if the work can begin sooner than currently planned. The work is currently scheduled to begin following the Labor Day weekend.

Thank you to all the residents along Glen Court and Glenridge that have been without driveway access for the past several days and upcoming week. Your patience and understanding is greatly appreciated.

Monday, August 17, 2015

Roadway Reconstruction on Glenridge and Glen Court Started

Work Completed Last Week:
·         Completed installation of storm sewer and storm services along Glenridge Drive and Glenayre Drive
·         Roadway layout / staking
·         Roadway excavation and aggregate base installation along Glenridge Drive
·         Tree Removal at Glen Court
·         All underground utility construction is now completed.

Work Anticipated This Week (Glenridge Drive and Glen Court):

·         Monday & Tuesday – Complete roadway excavation and aggregate base course installation.
·         Wednesday – Installation of String Line for concrete curb & gutter
o   Access to driveways restricted starting at 7:00 AM
·         Thursday – Grading and preparation work needed prior to concrete curb & gutter installation
·         Friday – Pour concrete curb & gutter.

The project has now moved into the roadway reconstruction phase. It is anticipated the roadway excavation and base course installation will be completed along Glenridge Drive and Glen Court near the middle of this week, with concrete curb & gutter installed prior to the end of the week.

With upcoming concrete curb & gutter installation and asphalt paving, we are requesting all residents along Glenridge Drive to have their vehicles removed from their driveways by 7:00 AM on Wednesday, August 19th. Residents will be able to access their driveways by Friday, August 28th, allowing 10 days for construction operations. Following concrete curb & gutter installation, the roadway will be graded and the first layer of asphalt pavement installed prior to access to driveways restored. We will be sure to keep all residents informed regarding potential delays or unforeseen circumstances that may extend the length of time access to driveways is restricted.

The roadway reconstruction along Glenayre Drive is anticipated to begin following the Labor Day weekend.

Thank you in advance to all those residents along Glenridge Drive who will be without driveways access starting the middle of next week. Your patience and understanding is greatly appreciated.

Monday, August 10, 2015

Undergroun Utility Construction Nearing End. Roadway Reconstruction to Begin

Work Completed Last Week:
·         Continued with storm sewer installation along Glenridge Drive and Glenayre Drive
·         Continued with storm sewer service installations along Glenridge Drive and Glenayre Drive.

Work Anticipated This Week:
·         Complete installation of storm sewer and storm sewer services.
·         Staking / layout for roadway reconstruction
·         Site clean-up prior to transitioning to roadway reconstruction phase.
·         Roadway excavation and aggregate base course installation along Glenridge Drive and Glen Court.

The majority of the underground utility improvements (water main, storm sewer, sanitary sewer) will be completed by the end of this week or early next week. The project will then be transitioning into the roadway reconstruction phase.

Exact dates are unknown, but the contractor is anticipating to begin roadway excavation and installation of aggregate base course later this week along Glenridge Drive and Glen Court. We are anticipating the concrete curb & gutter and 1st layer of asphalt pavement will be installed along Glenridge Drive and Glen Court prior to the Labor Day weekend. During the concrete curb & gutter and asphalt paving, residents will be restricted from utilizing their driveways. We will keep you notified regarding exact dates that driveway access will be restricted.

The roadway reconstruction along Glenayre Drive is anticipated to begin following the Labor Day weekend.

The coming weeks will have significant inconveniences to all residents along Glenridge Drive, Glen Court, and Glenayre Drive due to access to driveways being restricted for an extended period of time. Please be assured, we will do everything possible to ensure access to your driveways is restricted for the least amount of time possible. We thank you in advance for your patience and understanding.

Friday, July 31, 2015

Storm Sewer Installation On-Going

Work Completed Last Week:
·         Storm sewer main line along Glenayre Drive
·         Started storm sewer installation along Glenridge Drive

Work Anticipated This Week:
·         Continue with storm sewer installation along Glenridge Drive and Glenayre Drive.
·         Begin storm sewer service installations along Glenayre Drive and Glenridge Drive

Thank you again for all your patience and understanding during the construction operations.

Monday, July 27, 2015

Water Main and Service Replacements Completed

Work Completed Last Week:
·         Water service replacements along Glenridge Drive
·         Water service replacements along Glen Court
·         Connection between existing water main and new water main at the intersection of Central Road and Glenridge Drive.
·         Continued with storm sewer installation along Glenayre Drive.
·         Water main and service replacement is now completed.

 Work Anticipated This Week:
·         Complete storm sewer installation along Glenayre Drive
·         Begin storm sewer installation along Glenridge Drive
·         Continue with storm sewer service installations along Glenayre Drive and Glenridge Drive
·         Abandon old fire hydrants and valves.

Now that the water main replacement is completed, we do not anticipate any further water main shut downs. Thank you for your patience and understanding during disruptions to your water service over the past few weeks.

Monday, July 20, 2015

Water Service Replacement Continues

Work Completed Last Week:
·         Installed storm sewer along Glenayre Drive from Central Road to Glenridge Drive
·         Started installation of storm sewer services along Glenayre Drive.
·         Started water service replacements along Glenridge Drive
·         Connected new water main to existing water main at intersection of Central Road and Glenayre Drive.

Work Anticipated This Week:
·         Complete water service replacements along Glenridge Drive
·         Water service replacements along Glen Court
·         Connect existing water main to newly installed water main at the intersection of Glenridge Drive and Central Road
·         Begin storm sewer installation along Glenridge Drive

New water services are being installed from the new water main to the existing b-box within the Village right-of-way. New services will not be installed all the way to your home. During water service installation, water to individual homes will be turned off while the transition is made. Typically the water is turned off for 1-hour. The contractor will knock on the door of each home prior to turning off the water. It is difficult to determine the exact timing of the water shut-off; therefore, 24-hour notice is not given. The contractor will work with you to determine the best time to shut-off the water to the greatest extent possible.

Water service replacement along Glen Court are scheduled for Tuesday and Wednesday, July 21st and 22nd, this week. Due to construction activity within the cul-de-sac, we are requesting residents park their vehicles along Glenridge Drive during normal working hours (7 AM to 5 PM). Thank you in advance for all your patience during this time.


Thank you to all those residents that were without water for a period of time on Friday during the connection between the existing and newly installed water mains at the intersection of Glenayre Drive and Central Road. Another water main shut down for the connection at Glenridge Drive and Central Road is scheduled for this week. Residents will be notified 24 hours in advance of any water main shut down.

Friday, July 10, 2015

Water Service Replacement and Storm Sewer On-Going

Work Completed Last Week:
·         Completed water service replacements along Glenayre Drive
·         Completed required testing of newly installed water main along Glenridge Drive and Glen Court
·         Began storm sewer installation along Glenayre Drive.

Work Anticipated This Week:
·         Continue with storm sewer installation along Glenayre Drive
·         Begin water service replacements along Glenridge Drive and Glen Court

New water services are being installed from the new water main to the existing b-box within the Village right-of-way. New services will not be installed all the way to your home. During water service installation, water to individual homes will be turned off while the transition is made. Typically the water is turned off for 1-hour. The contractor will knock on the door of each home prior to turning off the water. It is difficult to determine the exact timing of the water shut-off; therefore, 24-hour notice is not given. The contractor will work with you to determine the best time to shut-off the water to the greatest extent possible.

We have been attempting to contact each of the residents along the project site that are getting a storm sewer service stub to determine the location of existing drains or preferred location of the service. If you have not been contacted yet, please request to speak with Jeff Yonke on-site. If you cannot find Jeff Yonke onsite, please contact Russ Jensen at 847-904-4418 or rjensen@glenview.il.us to schedule a time to meet.

Your assistance and cooperation in these matters is greatly appreciated.