·
Installed storm sewer along Glenayre Drive from
Central Road to Glenridge Drive
·
Started installation of storm sewer services
along Glenayre Drive.
·
Started water service replacements along
Glenridge Drive
·
Connected new water main to existing water main
at intersection of Central Road and Glenayre Drive.
Work Anticipated This Week:
·
Complete water service replacements along
Glenridge Drive
·
Water service replacements along Glen Court
·
Connect existing water main to newly installed
water main at the intersection of Glenridge Drive and Central Road
·
Begin storm sewer installation along Glenridge
Drive
New water services are being installed from the new water
main to the existing b-box within the Village right-of-way. New services will not
be installed all the way to your home. During water service installation, water
to individual homes will be turned off while the transition is made. Typically
the water is turned off for 1-hour. The contractor will knock on the door of
each home prior to turning off the water. It is difficult to determine the
exact timing of the water shut-off; therefore, 24-hour notice is not given. The
contractor will work with you to determine the best time to shut-off the water
to the greatest extent possible.
Water service replacement along Glen Court are scheduled for
Tuesday and Wednesday, July 21st and 22nd, this week. Due
to construction activity within the cul-de-sac, we are requesting residents
park their vehicles along Glenridge Drive during normal working hours (7 AM to
5 PM). Thank you in advance for all your patience during this time.
Thank you to all those residents that were without water for
a period of time on Friday during the connection between the existing and newly
installed water mains at the intersection of Glenayre Drive and Central Road.
Another water main shut down for the connection at Glenridge Drive and Central
Road is scheduled for this week. Residents will be notified 24 hours in
advance of any water main shut down.