Monday, October 12, 2015

General Clean-Up Last Week. Sod Installation This Week.

Work Completed Last Week:
·         Televising of new underground utilities
·         Final testing of underground utilities
·         Landscape grading
·         Installation of topsoil
·         Internal lining of sanitary sewers along Glenayre Drive
·         Miscellaneous site clean-up and tasks

Work Anticipated This Week
·         Topsoil Installation and final landscape grading
·         Sod Installation
·         Complete televising of new underground utilities

The contractor has continued to perform miscellaneous tasks around the project in preparation for paving the final surface layer along the entire project site. The final surface layer is typically one of the last items completed to minimize the amount of construction traffic on the surface. Currently, the final surface paving is scheduled for the week of October 12th.

At this time, residents can begin contacting their irrigation and brick driveway contractors to begin having those items restored.