Paving of first two layers of asphalt pavement.
·
Landscape grading behind previously installed
concrete curb & gutter.
·
Fine grading of roadway
·
Asphalt driveway restoration
·
Concrete driveway restoration
·
Access to driveways is allowed as of Friday,
August 28th.
Work Anticipated This Week
·
Install and grade topsoil along Glenridge Drive
and Glen Court
·
Removal of existing driveways along Glenayre
Drive, temporary access will be provided.
·
Staking / Layout for roadways improvements along
Glenayre Drive
·
Removal of existing asphalt pavement along
Glenayre Drive
·
Excavating of existing materials to sub-grade
along Glenayre Drive
·
Installation of aggregate base along Glenayre
Drive
Driveway access has been restored along Glenridge Drive and
Glen Court due to the concrete curb & gutter installation and asphalt
paving. Thank you to all those residents that were without access to your
driveways for approximately 10 days, your patience and understanding was
greatly appreciated.
The contractor will continue to grade and clean-up Glenridge
Drive and Glen Court in preparation for landscape and sod restoration over the
next week or so.
The contractor will also begin the roadway reconstruction
phase along Glenayre Drive. Work will include removal of existing driveways,
construction layout, roadway excavation, and installation of aggregate base
course.
The current schedule has the contractor performing concrete
curb & gutter installation and asphalt paving beginning the week of
September 14th through September 24th, depending on work
progress and weather conditions.
Thank you again to all the residents that have been living
in the construction area for the past several months. We understand the
difficulties and inconveniences that are caused with living through a
construction project and are doing everything possible to make the project go
as quickly as possible.