·
Completed installation of storm sewer and storm
services along Glenridge Drive and Glenayre Drive
·
Roadway layout / staking
·
Roadway excavation and aggregate base
installation along Glenridge Drive
·
Tree Removal at Glen Court
·
All underground utility construction is now
completed.
Work Anticipated This Week (Glenridge Drive and Glen
Court):
·
Monday & Tuesday – Complete roadway
excavation and aggregate base course installation.
·
Wednesday – Installation of String Line for
concrete curb & gutter
o Access
to driveways restricted starting at 7:00 AM
·
Thursday – Grading and preparation work needed
prior to concrete curb & gutter installation
·
Friday – Pour concrete curb & gutter.
With upcoming concrete curb & gutter installation and
asphalt paving, we are requesting all residents along Glenridge Drive to
have their vehicles removed from their driveways by 7:00 AM on Wednesday,
August 19th. Residents will be able to access their driveways by
Friday, August 28th, allowing 10 days for construction operations.
Following concrete curb & gutter installation, the roadway will be graded
and the first layer of asphalt pavement installed prior to access to driveways
restored. We will be sure to keep all residents informed regarding potential
delays or unforeseen circumstances that may extend the length of time access to
driveways is restricted.
The roadway reconstruction along Glenayre Drive is
anticipated to begin following the Labor Day weekend.
Thank you in advance to all those residents along Glenridge
Drive who will be without driveways access starting the middle of next week.
Your patience and understanding is greatly appreciated.