Work Completed Last Week (Glenayre Drive):

·         Install concrete curb and gutter from Glenview Rd. to Westview Rd.

·         Continued excavation of roadway and installation of new aggregate base materials.

·         Installation of curb string line and preparation for curb installation from Westview Rd. to Central Rd.


Work Anticipated This Week (Glenayre Drive)

·         Install concrete curb and gutter from Westview Rd. to Central Rd.

·         Backfill behind new curb and gutter.

·         Prep for asphalt and concrete driveway replacement.

·         Install asphalt and concrete driveway pavement.

·         Pave first two layers of asphalt roadway pavement.

 
The major roadway reconstruction of Glenayre Drive will continue this week as concrete curb & gutter poured, and first two layers of asphalt pavement paved. The current schedule due to a rain delay has concrete curb & gutter pouring to begin the week of September 21st and asphalt pavement installed by end the of the week, depending on work progress and weather conditions. Residents will be notified of driveway restrictions as the scheduled is finalized.

 