Monday, October 26, 2015

Sod Completed. Surface Paving this Week.

Work Completed Last Week:
·         Installation of topsoil and fine grading landscaped areas.
·         Sod Installation
·         Final Walk-through to find areas that need repair.

Work Anticipated This Week
·         Paving of asphalt surface
·         Making final repairs to items as identified with final walk-through.  

The paving of asphalt surface was pushed back to allow for sufficient time to get the sod restoration completed. A thin layer of oil will be placed on the existing asphalt surface prior to the final layer of asphalt being paved. Sand will also be placed on driveways and the roadway. This will help from tracking the oil on your concrete or brick driveways as well as help splattering on your vehicle. We do ask that you drive slowly over the fresh layer of oil.

Asphalt surface paving is scheduled for Monday, October 26th.  We will ask that you minimize your trips along the roadways and no parking will be allowed on the streets. Access along the streets will also likely be restricted due to the paving operations and number of trucks within the area.

Once the final layer of asphalt is installed, the major construction operations of the project will be completed with a few minor repairs and restoration items to be completed.

Thanks again for all your patience during these past several months you have been living in a construction zone.

Monday, October 19, 2015

Final Surface Paving and Sod Restoration This Week.

Work Completed Last Week:
·         Installation of topsoil and fine grading landscaped areas.
·         Televising of new underground utilities
·         Final testing of underground utilities
·         Miscellaneous site clean-up and tasks

Work Anticipated This Week
·         Topsoil Installation and final landscape grading
·         Sod Installation
·         Making final repairs to items as identified with final walk-through.
·         Paving of asphalt surface 

The current schedule has the contractor completing any minor repairs and finishing the sod installation the beginning of this week with the final layer of asphalt pavement installed on Thursday or Friday. A thin layer of oil will be placed on the existing asphalt surface prior to the final layer of asphalt being paved. Sand will also be placed on driveways and the roadway. This will help from tracking the oil on your concrete or brick driveways as well as help splattering on your vehicle. We do ask that you drive slowly over the fresh layer of oil.  

Residents will be notified of the exact day for final asphalt paving. We will ask that you minimize your trips along the roadways and no parking will be allowed on the streets. Access along the streets will also likely be restricted due to the paving operations and number of trucks within the area.  

Once the final layer of asphalt is installed, the major construction operations of the project will be completed with a few minor repairs and restoration items to be completed. 

Thanks again for all your patience during these past several months you have been living in a construction zone.

Monday, October 12, 2015

General Clean-Up Last Week. Sod Installation This Week.

Work Completed Last Week:
·         Televising of new underground utilities
·         Final testing of underground utilities
·         Landscape grading
·         Installation of topsoil
·         Internal lining of sanitary sewers along Glenayre Drive
·         Miscellaneous site clean-up and tasks

Work Anticipated This Week
·         Topsoil Installation and final landscape grading
·         Sod Installation
·         Complete televising of new underground utilities

The contractor has continued to perform miscellaneous tasks around the project in preparation for paving the final surface layer along the entire project site. The final surface layer is typically one of the last items completed to minimize the amount of construction traffic on the surface. Currently, the final surface paving is scheduled for the week of October 12th.

At this time, residents can begin contacting their irrigation and brick driveway contractors to begin having those items restored.

Monday, October 5, 2015

Final Testing of Underground Utilities On-Going

Work Completed Last Week (Glenayre Drive):
·         Adjust manhole structures within pavement
·         Complete asphalt driveway restorations
·         Continued with landscape grading
·         Miscellaneous site clean-up and tasks 

Work Anticipated This Week
·         Televising of new underground utilities
·         Final testing of underground utilities
·         Topsoil Installation
·         Sod Installation

The contractor has continued to perform miscellaneous tasks around the project in preparation for paving the final surface layer along the entire project site. The final surface layer is typically one of the last items completed to minimize the amount of construction traffic on the surface. Currently, the final surface paving is scheduled for the week of October 12th.

At this time, residents can begin contacting their irrigation and brick driveway contractors to begin having those items restored.