Tuesday, November 3, 2015

Project Completed!!

Work Completed Last Week:
·         Asphalt surface paving.
·         Miscellaneous repairs of items identified during final walk-through.

With the completion of the asphalt surface paving this week, along with a few other miscellaneous items completed, the major construction along the project site is now completed. There are still a few outstanding issues that we are addressing on an individual basis and will completed in the near future.

We would like to thank all the residents within the Glenayre Park neighborhood for dealing with the construction over the past two years. We understand what an inconvenience construction causes to your daily lives. We thank everyone for their patience and understanding. We are hopeful that you are satisfied with the end result.

Within the next few weeks the Village of Glenview will send out a survey for you to complete. We appreciate your time in completing the survey as it assistance with future projects throughout the Village.

This will also be the last Blog Post for the project. Again, we hope you found the information provided beneficial.

If you have any additional concerns, please contact the project manager, Robert Steele, at 847-904-4423

Monday, October 26, 2015

Sod Completed. Surface Paving this Week.

Work Completed Last Week:
·         Installation of topsoil and fine grading landscaped areas.
·         Sod Installation
·         Final Walk-through to find areas that need repair.

Work Anticipated This Week
·         Paving of asphalt surface
·         Making final repairs to items as identified with final walk-through.  

The paving of asphalt surface was pushed back to allow for sufficient time to get the sod restoration completed. A thin layer of oil will be placed on the existing asphalt surface prior to the final layer of asphalt being paved. Sand will also be placed on driveways and the roadway. This will help from tracking the oil on your concrete or brick driveways as well as help splattering on your vehicle. We do ask that you drive slowly over the fresh layer of oil.

Asphalt surface paving is scheduled for Monday, October 26th.  We will ask that you minimize your trips along the roadways and no parking will be allowed on the streets. Access along the streets will also likely be restricted due to the paving operations and number of trucks within the area.

Once the final layer of asphalt is installed, the major construction operations of the project will be completed with a few minor repairs and restoration items to be completed.

Thanks again for all your patience during these past several months you have been living in a construction zone.

Monday, October 19, 2015

Final Surface Paving and Sod Restoration This Week.

Work Completed Last Week:
·         Installation of topsoil and fine grading landscaped areas.
·         Televising of new underground utilities
·         Final testing of underground utilities
·         Miscellaneous site clean-up and tasks

Work Anticipated This Week
·         Topsoil Installation and final landscape grading
·         Sod Installation
·         Making final repairs to items as identified with final walk-through.
·         Paving of asphalt surface 

The current schedule has the contractor completing any minor repairs and finishing the sod installation the beginning of this week with the final layer of asphalt pavement installed on Thursday or Friday. A thin layer of oil will be placed on the existing asphalt surface prior to the final layer of asphalt being paved. Sand will also be placed on driveways and the roadway. This will help from tracking the oil on your concrete or brick driveways as well as help splattering on your vehicle. We do ask that you drive slowly over the fresh layer of oil.  

Residents will be notified of the exact day for final asphalt paving. We will ask that you minimize your trips along the roadways and no parking will be allowed on the streets. Access along the streets will also likely be restricted due to the paving operations and number of trucks within the area.  

Once the final layer of asphalt is installed, the major construction operations of the project will be completed with a few minor repairs and restoration items to be completed. 

Thanks again for all your patience during these past several months you have been living in a construction zone.

Monday, October 12, 2015

General Clean-Up Last Week. Sod Installation This Week.

Work Completed Last Week:
·         Televising of new underground utilities
·         Final testing of underground utilities
·         Landscape grading
·         Installation of topsoil
·         Internal lining of sanitary sewers along Glenayre Drive
·         Miscellaneous site clean-up and tasks

Work Anticipated This Week
·         Topsoil Installation and final landscape grading
·         Sod Installation
·         Complete televising of new underground utilities

The contractor has continued to perform miscellaneous tasks around the project in preparation for paving the final surface layer along the entire project site. The final surface layer is typically one of the last items completed to minimize the amount of construction traffic on the surface. Currently, the final surface paving is scheduled for the week of October 12th.

At this time, residents can begin contacting their irrigation and brick driveway contractors to begin having those items restored.

Monday, October 5, 2015

Final Testing of Underground Utilities On-Going

Work Completed Last Week (Glenayre Drive):
·         Adjust manhole structures within pavement
·         Complete asphalt driveway restorations
·         Continued with landscape grading
·         Miscellaneous site clean-up and tasks 

Work Anticipated This Week
·         Televising of new underground utilities
·         Final testing of underground utilities
·         Topsoil Installation
·         Sod Installation

The contractor has continued to perform miscellaneous tasks around the project in preparation for paving the final surface layer along the entire project site. The final surface layer is typically one of the last items completed to minimize the amount of construction traffic on the surface. Currently, the final surface paving is scheduled for the week of October 12th.

At this time, residents can begin contacting their irrigation and brick driveway contractors to begin having those items restored.

Monday, September 28, 2015

Concrete Curb & Gutter and First Layer of Asphalt Completed. Landscape Restoration to Begin

Work Completed Last Week (Glenayre Drive):
·         Concrete curb & gutter installation
·         Fine grading of roadway
·         Rough grading of landscape areas behind cub & gutter
·         Paving of first layer of asphalt pavement
·         Asphalt driveway restorations

Work Anticipated This Week
·         Adjust manhole structures within the pavement
·         Topsoil installation
·         Fine grade landscape restorations
·         Sod installation
·         Perform miscellaneous testing prior to final asphalt surface
 
Thank you to all the residents along Glenayre Drive that have been without access to your driveways for almost 2 weeks. Your patience and understanding has been greatly appreciated. With the first layer of asphalt pavement being completed, the amount of dust will be greatly reduced, as well as providing a smooth surface to drive on.

The contractor will continue to perform landscape restorations and begin performing final project testing for the next few weeks. Once all inspections and tests have passed, sod installed, and other miscellaneous tasks completed, the final asphalt surface layer will be installed along the entire project site including Glenayre Drive, Glenridge Drive, and Glen Court.

Thank you again to all the residents within the project site has you have been dealing with the dusty conditions and rough roads for several months now. Hopefully, you are beginning to see the end of the light and pleased with the final project.

At this time, residents can begin contacting their irrigation and brick driveway contractors to begin having those items restored.

Monday, September 21, 2015


Work Completed Last Week (Glenayre Drive):

·         Install concrete curb and gutter from Glenview Rd. to Westview Rd.

·         Continued excavation of roadway and installation of new aggregate base materials.

·         Installation of curb string line and preparation for curb installation from Westview Rd. to Central Rd.


Work Anticipated This Week (Glenayre Drive)

·         Install concrete curb and gutter from Westview Rd. to Central Rd.

·         Backfill behind new curb and gutter.

·         Prep for asphalt and concrete driveway replacement.

·         Install asphalt and concrete driveway pavement.

·         Pave first two layers of asphalt roadway pavement.

 
The major roadway reconstruction of Glenayre Drive will continue this week as concrete curb & gutter poured, and first two layers of asphalt pavement paved. The current schedule due to a rain delay has concrete curb & gutter pouring to begin the week of September 21st and asphalt pavement installed by end the of the week, depending on work progress and weather conditions. Residents will be notified of driveway restrictions as the scheduled is finalized.

 
Thank you again for all your patience and understanding.