Monday, May 4, 2015

Prep Work to Begin This Week. Underground Construction to Begin week of May 11th.

Work Completed Last Week:
·         None

 Work Anticipated This Week:
·         Complete landscape restoration of Phase I Improvements.
·         Grinding-in-place of existing asphalt pavement
·         Mobilization of equipment
·         General preparatory work in prior to excavation beginning 

We anticipate the contractor will begin sanitary sewer service replacements along Glenayre Drive the week of May 11th.