2 Layers of Apshalt Paved on Glenridge. Roadway Reconstruction to Begin on Glenayre

Work Completed Last Week (Glenridge Drive and Glen Court):
·         Paving of first two layers of asphalt pavement.
·         Landscape grading behind previously installed concrete curb & gutter.
·         Fine grading of roadway
·         Asphalt driveway restoration
·         Concrete driveway restoration
·         Access to driveways is allowed as of Friday, August 28th

Work Anticipated This Week
·         Install and grade topsoil along Glenridge Drive and Glen Court
·         Removal of existing driveways along Glenayre Drive, temporary access will be provided.
·         Staking / Layout for roadways improvements along Glenayre Drive
·         Removal of existing asphalt pavement along Glenayre Drive
·         Excavating of existing materials to sub-grade along Glenayre Drive
·         Installation of aggregate base along Glenayre Drive

Driveway access has been restored along Glenridge Drive and Glen Court due to the concrete curb & gutter installation and asphalt paving. Thank you to all those residents that were without access to your driveways for approximately 10 days, your patience and understanding was greatly appreciated.

The contractor will continue to grade and clean-up Glenridge Drive and Glen Court in preparation for landscape and sod restoration over the next week or so.

The contractor will also begin the roadway reconstruction phase along Glenayre Drive. Work will include removal of existing driveways, construction layout, roadway excavation, and installation of aggregate base course.

The current schedule has the contractor performing concrete curb & gutter installation and asphalt paving beginning the week of September 14th through September 24th, depending on work progress and weather conditions.

Thank you again to all the residents that have been living in the construction area for the past several months. We understand the difficulties and inconveniences that are caused with living through a construction project and are doing everything possible to make the project go as quickly as possible.

Monday, August 24, 2015

Roadway Improvements along Glenridge Drive and Glen Court Continue

Work Completed Last Week (Glenridge Drive and Glen Court)
·         Completed roadway excavation and installation of aggregate base course
·         Grading, setting string line, and structure adjustments in preparation of concrete curb & gutter
·         Pouring of concrete curb & gutter.

Work Anticipated This Week (Glenridge Drive and Glen Court):
·         Grading and backfilling along back side of curb & gutter
·         Grading of roadway in preparation for asphalt pavement
·         Grading for asphalt driveway replacement
·         Installation of first layer for asphalt driveway replacement
·         Paving first layers of asphalt pavement, scheduled for Wednesday or Thursday.

Driveway access to those residents along Glenridge Drive and Glen Court is scheduled to be allowed by Friday, August 28th. Access might be allowed sooner depending on work progress.                                                                                                                                                                                                                        

The week of August 31st, the contractor will continue with landscape grading, topsoil installation, and general site clean-up prior to the Labor Day weekend.

The schedule for roadway reconstruction along Glenayre Drive is currently being evaluated to determine if the work can begin sooner than currently planned. The work is currently scheduled to begin following the Labor Day weekend.

Thank you to all the residents along Glen Court and Glenridge that have been without driveway access for the past several days and upcoming week. Your patience and understanding is greatly appreciated.

Monday, August 17, 2015

Roadway Reconstruction on Glenridge and Glen Court Started

Work Completed Last Week:
·         Completed installation of storm sewer and storm services along Glenridge Drive and Glenayre Drive
·         Roadway layout / staking
·         Roadway excavation and aggregate base installation along Glenridge Drive
·         Tree Removal at Glen Court
·         All underground utility construction is now completed.

Work Anticipated This Week (Glenridge Drive and Glen Court):

·         Monday & Tuesday – Complete roadway excavation and aggregate base course installation.
·         Wednesday – Installation of String Line for concrete curb & gutter
o   Access to driveways restricted starting at 7:00 AM
·         Thursday – Grading and preparation work needed prior to concrete curb & gutter installation
·         Friday – Pour concrete curb & gutter.

The project has now moved into the roadway reconstruction phase. It is anticipated the roadway excavation and base course installation will be completed along Glenridge Drive and Glen Court near the middle of this week, with concrete curb & gutter installed prior to the end of the week.

With upcoming concrete curb & gutter installation and asphalt paving, we are requesting all residents along Glenridge Drive to have their vehicles removed from their driveways by 7:00 AM on Wednesday, August 19th. Residents will be able to access their driveways by Friday, August 28th, allowing 10 days for construction operations. Following concrete curb & gutter installation, the roadway will be graded and the first layer of asphalt pavement installed prior to access to driveways restored. We will be sure to keep all residents informed regarding potential delays or unforeseen circumstances that may extend the length of time access to driveways is restricted.

The roadway reconstruction along Glenayre Drive is anticipated to begin following the Labor Day weekend.

Thank you in advance to all those residents along Glenridge Drive who will be without driveways access starting the middle of next week. Your patience and understanding is greatly appreciated.

Monday, August 10, 2015

Undergroun Utility Construction Nearing End. Roadway Reconstruction to Begin

Work Completed Last Week:
·         Continued with storm sewer installation along Glenridge Drive and Glenayre Drive
·         Continued with storm sewer service installations along Glenridge Drive and Glenayre Drive.

Work Anticipated This Week:
·         Complete installation of storm sewer and storm sewer services.
·         Staking / layout for roadway reconstruction
·         Site clean-up prior to transitioning to roadway reconstruction phase.
·         Roadway excavation and aggregate base course installation along Glenridge Drive and Glen Court.

The majority of the underground utility improvements (water main, storm sewer, sanitary sewer) will be completed by the end of this week or early next week. The project will then be transitioning into the roadway reconstruction phase.

Exact dates are unknown, but the contractor is anticipating to begin roadway excavation and installation of aggregate base course later this week along Glenridge Drive and Glen Court. We are anticipating the concrete curb & gutter and 1st layer of asphalt pavement will be installed along Glenridge Drive and Glen Court prior to the Labor Day weekend. During the concrete curb & gutter and asphalt paving, residents will be restricted from utilizing their driveways. We will keep you notified regarding exact dates that driveway access will be restricted.

The roadway reconstruction along Glenayre Drive is anticipated to begin following the Labor Day weekend.

The coming weeks will have significant inconveniences to all residents along Glenridge Drive, Glen Court, and Glenayre Drive due to access to driveways being restricted for an extended period of time. Please be assured, we will do everything possible to ensure access to your driveways is restricted for the least amount of time possible. We thank you in advance for your patience and understanding.