Storm Sewer Installation to Begin

Work Completed Last Week:
·         Water main installation along Glenridge Drive
·         Water main installation along Glen Court.
·         Required testing of newly installed water main along Glenayre Drive

Work Anticipated This Week:
·         Required testing of newly installed water main along Glenridge Drive and Glen Court
·         Storm sewer installation along Glenayre Drive and Glenridge Drive
·         Water service replacements.

The mainline water main is now completed, with the required testing of the newly installed water main on-going. At this time, the contractor will begin working on the storm sewer installation along Glenayre Drive and Glenridge Drive. The contractor may also begin to install water services to individual homes once the required testing is performed and accepted.

New water services will be installed from the new water main to the existing b-box within the Village right-of-way. New services will not be installed all the way to your home. During water service installation, water to individual homes will be turned off while the transition is made. Typically the water is turned off for 1-hour. The contractor will knock on the door of each home prior to turning off the water. It is difficult to determine the exact timing of the water shut-off; therefore, 24-hour notice is not given. The contractor will work with you to determine the best time to shut-off the water to the greatest extent possible.

Monday, June 22, 2015

Water Main Installation On-Going

Work Completed Last Week:
·         Water main installation along Glenayre Drive from Westview Road to Central Road
·         Concrete pathway paving at Central Road and Glendale Drive

 Work Anticipated This Week:
·         Water main installation along Glenridge Drive, starting at Glenayre Drive working south
·         Water main installation along Glen Court

Thank you to all those residents that were without water for a period of time on Monday due to the water main connection between the new and existing systems and Glenayre Drive and Westview Road. Water main shut-downs will occur on occasion in the coming weeks as the new water main is connected to the existing water main. Residents will be notified 24-hours in advance of any scheduled water main shut-down.

As you may realize, construction can be unpredictable. This was the case on Monday afternoon when an unmarked electric line was damaged during construction and caused a wide-spread power outage throughout the neighborhood. We appreciate your understanding as the situation was resolved as quickly as possible.

Friday, June 12, 2015

Sanitary Sewer Improvements Completed. Water Main Begins This Week.

Work Completed Last Week:
·         Sanitary sewer improvements along Glen Court
·         General site clean-up.
·         Work in preparation for starting water main construction.
·         All sanitary sewer improvements along the project site are now completed.

Work Anticipated This Week:
·         Begin water main installation on Glenayre Drive starting at Westview Drive and working south to Central Road.
·         Water main installation along Glenridge Drive starting at Glenayre Drive and working south to Central Road.

As the water main replacement begins, there will be instances when the water main will need to be shut-down to perform connections between the existing and new systems. These shut-downs typically last between 4 and 6 hours. Residents will be notified 24-hours in advance prior to any scheduled water main shut-down.

Thank you to those residents along Glen Court that had limited access to their driveways during last week’s sanitary sewer improvements, your patience and understanding was greatly appreciated.

Friday, June 5, 2015

Sanitary Sewer Improvements along Glen Court to Continue. Water Main to Begin on Glenayre

Work Completed Last Week:
·         Sanitary sewer service replacements along Glenridge Drive and Glen Court
·         Sanitary manhole replacements along Glenridge Drive
·         Sanitary sewer mainline repairs as needed along Glenridge Drive.

 Work Anticipated This Week:
·         Continue with sanitary sewer service replacements along Glen Court
·         Sanitary sewer manhole replacements along Glen Court
·         Sanitary sewer mainline repairs as needed along Glen Court
·         Water main installation along Glenayre Drive.

We understanding living in a construction zone causes many disruptions and inconveniences. We thank you for your patience and understanding. We especially appreciate those residents that are unable to access their driveways along Glen Court during work hours due to sanitary sewer repairs.

Monday, June 1, 2015

Sanitary Sewer Repairs Continue

Work Completed Last Week:
·         Sanitary sewer service replacements along Glenayre Drive and Glenridge Drive
·         Sanitary manhole replacements along Glenayre Drive
·         Sanitary sewer mainline repairs as needed.

Work Anticipated This Week:
·         Continue with sanitary sewer service replacements along Glenridge Drive and Glen Court
·         Continue with sanitary sewer manhole replacements along Glenridge Drive and Glen Court

We appreciate your continued patience and understanding during the construction operations.